Precautions for Asphalt Pavement Construction in Winter
- Share
- Issue Time
- Jan 4,2024
For asphalt pavement construction in winter, we need to
follow a series of precautions. These suggestions not only meet market
requirements, but also help ensure construction quality and extend the service
life of roads.
1. Temperature monitoring and management
1) Ensure that the temperature of the air and bitumen is
within the allowable range of the engineering specifications. Usually, the air temperature
should be higher than 5℃,
and the factory temperature of the asphalt mixture should not be lower than 150℃.
2) Use insulation facilities such as heaters or insulation
materials to maintain the temperature of the mixing equipment.
2. Material selection and storage
1) Use asphalt mixture that has been specially treated or
modified with additives to enhance its performance under low temperature
conditions.
2) Ensure that all construction materials such as bitumen and
aggregate are properly insulated and stored in a dry, well-ventilated area.
3. Construction time planning
1) Choose a time of day with higher temperatures for
construction, avoiding the cold period after sunset.
2) Shorten the construction period and reduce the exposure
time of materials at low temperatures.
4. Mixing and transportation
1) During the mixing process, make sure to mix evenly at a
proper temperature.
2) Tidy up the carriage before loading. During
transportation, prevent the mixture from sticking to the bottom of the
carriage, which should be coated with anti-adhesive or release agent.
3) Ensure that the mixture is not affected by sudden braking,
sharp turns, or bumps during transportation.
5. Paving and rolling
1) Use a vibratory tamper with a high frequency to ensure
that the density meets the requirements.
2) Use a small-tonnage roller for initial rolling, avoiding
the use of rubber-tired rollers.
3) Avoid opening the traffic before the road temperature
drops to 50℃.
6. Quality inspection and control
1) Conduct more Marshall tests for molding and ensure their
authenticity and reliability.
2) Carry out more on-site drill core samplings and ensure
their quality, focusing on inspecting indicators such as the density and
porosity of the asphalt mixture.
7. Safety and environmental protection
1) Check mechanical equipment regularly to ensure its normal
operation, and strengthen safety management on the construction site.
2) Set up obvious safety warning signs and safety protection
facilities.
3) Control the emission of construction noise, wastewater and
exhaust gas, so as to minimize the impact on the surrounding environment.
8. Other precautions:
1) Strengthen the connection with local meteorological
department, in order to understand the weather changes and take measures in a
timely manner.
2) Pay attention to the temperature change of the mixture to
prevent abnormalities.
3) Enhance the management and supervision of the construction
site to ensure the effective implementation of various measures.
4) Strengthen communication and coordination with relevant
government agencies to ensure smooth construction.
In conclusion, the construction of asphalt pavement in winter
calls for special attention to issues such as quality, safety, and
environmental protection. Bearing the suggestions in mind, it is possible to
effectively complete the task of asphalt pavement construction under severe
winter conditions.